What Was Needed?
Changes to the heating plant called for new electrical supplies and control wiring to serve a Flamco pressurisation and pressure monitoring unit, a degasser and a de-stratification pump. The equipment also needed connections to the building’s central building management system (BMS). The request came with a short lead time.
What Electrical Work Was Completed?
- Electrical supplies and control wiring for the pressurisation and pressure monitoring equipment.
- Electrical supplies and control wiring for the degasser and de-stratification pump.
- Control wiring brought back to the central BMS, with minor interface adaptations carried out by the lead engineer.
- Coordination of the electrical connections and controls interfaces so the specialist BMS partners could carry out their tie-in work.
The work was planned and completed within five days of the initial contact. The installation took place around existing heating plant and building services infrastructure.
What Was the Outcome?
The electrical supplies and control wiring are complete. The equipment interfaces are ready for the specialist BMS partners to tie in as the wider heating refurbishment progresses.
This electrical scope was undertaken by IN-TECH’s lead engineer as part of a specialist subcontracting team supporting the wider heating refurbishment.